SALISBURY, Maryland — The City of Salisbury’s Department of Infrastructure and Development (DID) issues a schedule update for downtown sewer line cleaning, inspection, and smoke testing, with the contractor continuing the work on Saturday, September 13, 2025, for project completion.
Remaining work includes:
- Smoke testing across the full project area.
-
-
- E. Market Street
- W. Market Street
- Poplar Hill Avenue
- Baptist Street
- Calvert Street (between Baptist Street and Poplar Hill Avenue)
-
- Sewer cleaning and CCTV inspection on Baptist Street (between E. Main St. and E. Market St.) and Camden Street.
As with earlier phases:
- An updated notification letter will be distributed to affected businesses.
- Fire and police departments will again be notified in advance.
Residents and businesses are encouraged to review project updates and contact the City with any questions. To learn more visit https://salisbury.md/news.
###